There has always been undue academic pressure on Indian schools in capital area to accommodate growing number of wards of Indian expatriate community during the last one decade. With more than 3000 fresh admissions in every year coupled with nearly 3500 students undergoing afternoon classes, this growing need of having yet another school in the capital area was found to be the need of the hour by Board of Directors, Indian Schools in Oman. At the same time, such an initiative should also need to match with the requirements of civil authorities to effectively manage surrounding areas of capital schools through effective management of traffic.

. This initiative of Board of Directors received a shot in arm when Ministry of Housing, Sultanate of Oman granted permission to establish an Indian School at Al Awabi in the year 2011 in a land of about 15,000 Sq Mtrs. Subsequently, Ministry of Education granted permission to construct a school at the designated place in the year 2013 subject to the approval of Public Authority of Civil Defence & Ambulance, Directorate General of Traffic, and Director General of Operations. After having chalked various plans for fund mobilization for constructing the school and required permissions from civil authorities, the project to construct the school has been awarded to M/S. Al Nehda Al Omania Co. LLC. Project work commenced in the month of March 2017 and is expected to be complete by September 2018. The project includes swimming pool and gymnasium apart from academic facilities to cater for around 4500 students.

img
img
img
img

Ongoing project of Indian School Ibri consist of two projects;

Project 1

Two storey building which has total Eight identical class rooms and separate four tiolets. ie. Four class rooms and two bathrooms at the ground floor and four class rooms and two toilets in the 1st floor. In addition to these there are three well equipped laboratories including Chemistry lab, Physics lab and Biology lab. Total Area of Project 1 is 1000.00 SQ.M Status: Class rooms and toilets construction is under the final stage and Laboratory furnishing work has to be started.

Project 2

Construction of Auditorium stage

Status: Front stage towards the school auditorium has been completed and back stage towards the ground is still under construction.

img
img
img
img

Approximate completion of work: 75%

Details of work left out: Physical Work: 15% which includes Fixing of grills for windows, ELV systems , Air conditioning , Laboratories and Play grounds.

Commissioning Work and Statutory Approvals: 10% viz.from Fire, Water supply, Baladiya, Mazoon and MOE.

Tentative date proposed for shifting and inauguration: Mid September- 2018

.